Schedule Slippage Calculator

Use this free Schedule Slippage Calculator to determine whether your project is ahead or behind schedule. Enter the planned and actual durations to get your percentage of slippage.

Schedule Slippage Calculator

How Schedule Slippage is Calculated

Schedule Slippage (%) = ((Actual Duration − Planned Duration) ÷ Planned Duration) × 100. A positive result means the project is behind schedule; negative means ahead.

Example

If a project was planned for 60 days but took 66 days, slippage = ((66 − 60) ÷ 60) × 100 = 10% delay.