Budget Overrun Calculator

Use this free Budget Overrun Calculator to determine how much your project has exceeded its planned budget. Enter the planned and actual costs to find your overrun percentage.

Budget Overrun Calculator

How Budget Overrun is Calculated

Budget Overrun (%) = ((Actual Cost − Planned Budget) ÷ Planned Budget) × 100. This percentage indicates how much your project exceeded the planned cost.

Example

If your planned budget was $100,000 and actual cost was $110,000: Overrun = ((110,000 − 100,000) ÷ 100,000) × 100 = 10% overrun.