Use this free Budget Overrun Calculator to determine how much your project has exceeded its planned budget.
Enter the planned and actual costs to find your overrun percentage.
Many teams track cost overruns and schedule risks using calculators like this one, but they also rely on project management software to monitor budgets and task progress in real time. Our detailed ClickUp review explains how teams manage tasks, timelines, and project costs inside one integrated workspace.
Budget Overrun (%) = ((Actual Cost − Planned Budget) ÷ Planned Budget) × 100.
This percentage indicates how much your project exceeded the planned cost.
Example
If your planned budget was $100,000 and actual cost was $110,000:
Overrun = ((110,000 − 100,000) ÷ 100,000) × 100 = 10% overrun.